6.15 Testing of aggregates

Testing of unit inputs, outputs and parts can be done manually.

Go to settings and enter the authorisation code 123321.

Test parameters are displayed and they can be switched on and off and display values.

  • At control signal VVX the heat exchanger starts and runs in pulses after the control signal, (-1 = 100%).
  • In the case of a heating control signal, 230 Vac is also sent out on terminals 16 &17.
  • In the case of a cooling control signal, 230 Vac is also sent out on terminals 17 &18.

See Parameter settings.