6.11 Testing of aggregates

Testing of unit inputs, outputs and parts can be done manually.

Go to settings and enter the authorisation code 123321.

Test parameters are displayed and they can be switched on and off and display values.

  • At control signal VVX the heat exchanger starts and runs with heat output after the control signal, (value -1 = 100% & -2 = 50%).

See Parameter settings.

Reservation for errors or linguistic discrepancies that may have arisen during printing, translation or assisted text processing. In case of discrepancies between language versions, the original Swedish version applies. See conditions.